8.000m2 of façade finished in just 6 months, thanks to construction hoist and mast climbing platforms of Orion

Type of machine:

Application: Transport of goods and persons

For the Upkot project in Ghent, Deblaere, as the main contractor, asked us to provide the vertical transport on the project. The timing for this project was very short. We installed the first construction hoist in December 2019. At that time there was only the concrete structure up to the 8th floor. In February, we then installed the mast climbing platforms for the facade finishing. The entire 8,000m2 facade was ready in July 2020.

Our mast climbing platforms were chosen because they are easily adjustable during the construction site, so that the 3m high aluminium structures could be installed quickly.